19th St. Culvert Replacement (Nevada 29)
Project Map

19th St. Bridge replacement (Nevada 29)

A bridge in Nevada Township, section 29, on 19th street approximately 0.44 miles South of 260th St. is scheduled for replacement. The road will be closed for the removal of the existing bridge and construction of new twin culverts. Reilly Construction Co., Inc. of Ossian, Iowa will be performing the work. The project is expected to take approximately 1 month, depending on the weather. The Contractor is currently being held up by utilities.

Update: 9/2/2016
The culvert has been replaced and the road is now open.