E-18 Bridge Replacement

E-18 Detour Route Map

Bridge Replacement Project on E-18 (Warren Twp., Sec. 18&19)

Story county will be replacing a bridge on Co. Rd. E-18 (130th) approximately 400 feet east of Co. Rd. S-14 (620th). The road will be closed to traffic during construction. Peterson Contractors Inc., of Reinbeck, Iowa will be the prime contractor on the project. The project is expected to take approximately four months, depending on the weather. The Detour for this project will be south on S-14 then east on E-29 and then north on S-27 and the reverse.

UPDATE: 7/9/2021

The road closed Monday May 10th 2021. The Contractor has completed work on the new bridge. They are now working to complete the remaining dirt work and preping the bridge approaches for  roadway paving.